The new Kenilworth School development is now under construction which is due to open their doors for a new term at the beginning of September 2023.

The S278 works will primarily focus upon completing the areas immediately in front of the school first.  This will leave certain areas to be completed during the start of the autumn term.

Highway Construction Progress 

The highway contractor appointed by WCC are CR Reynolds.

Scheme remains on track for completion in Autumn 2023.

The contractor’s working hours will be 7am to 5pm Monday to Sunday, with certain operations restricted to after 8am to minimise disruption to residents.  The contractor has increased its hours of working at the weekends to ensure that the work on Glasshouse Lane is completed for the school opening on 1 September 2023.

The contractor is currently working on the east side of Glasshouse Lane widening the existing carriageway and installing drainage to ensure the programme remains on plan.

The traffic signals on Glasshouse Lane continue to be operational full-time to keep the travelling public and our work force on the ground safe.  These are being monitored at peak times to reduce traffic congestion.

Completed works to date

  • Footpath/cycle path works completed on the west side of Glasshouse Lane with final surface course to be completed at a later date.
  • Traffic signals ducting and chambers on the west side of Glasshouse Lane.
  • Road gulleys and connections on the west side of Glasshouse Lane.
  • Site clearance on the east side of Glasshouse Lane.
  • Excavation, kerb laying, and carriageway foundations completed on widened section of Glasshouse Lane.
  • Drainage works completed on widened section.

Planned works

Glasshouse Lane Road widening

  • Drainage 21 June – 4 August 2023.
  • Road construction 21 June – 31 August 2023.
  • Miller Homes installation of a new foul sewer and electrical supply cables – 10 July 2023 – 25 August 2023.
  • Leyes Lane footpaths – 14 September – 6 October 2023.
  • Dencer Drive toucan crossing – permanent works October, temporary controlled crossing to be installed for the school opening.
Image showing the widening of Glasshouse Lane kerbWidening of the northern section of Glasshouse Lane

Second image showing carriageway foundation of Glasshouse Lane wideningFurther progress of the northern section of Glasshouse Lane

Image showing widening progress near Kenilworth School entranceWidening of the middle section of Glasshouse Lane, near the new school entrance

Second image highlighting progress of the widening of Glasshouse Lane, by Kenilworth SchoolFurther progress of the middle section of Glasshouse Lane

Current considerations

Our primary focus will always be working with all parties to facilitate the schools opening on time.

Current considerations
Considerations Next steps
Trial holes have identified several unforeseen service connections that will need to be lowered (utilities) The construction depth of the new carriageway has been reduced by using a stronger foundation material. Thus, removing the need to divert utility services
Traffic Regulation Orders (TRO) to be advertised and approved to complete some of the features set out in the planning application. For example, the speed cushions TRO’s to be advertised, this is being followed up and a date for advert will be confirmed
Dencer Drive toucan crossing consultation is complete A report will be presented to the July Portfolio Holder decision making session
Part of the works will be completed post school opening The school’s project team will be engaged to promote joint communications with the staff, parents and students ready for the new term

Adjacent Developments in the area

Miller Homes are currently developing the site north of the new school. The plan is to complete all section S278 works together.

Miller Homes have drainage and service connections to be undertaken in the area. Works are currently being undertaken.

Vistry Homes will be developing the site south of the new school.

The S278 works include a new roundabout on the Stanfield Grove junction with a new footpath/cycle path connecting to the school’s footpath/cycle paths.

These works will commence after the School S278 works are complete and are planned for completion Spring 2024.

Communications

Programme updates can be found on the WCC S278 pages

Regular meetings are held with the school’s project team, the schools appointed consultants, and designers to discuss contract progress, design changes and communications.

We apologise for any inconvenience the works may cause and want to thank you, for your on-going continued support during the construction period.

Graham Hemmings WCC Project Lead (WCC Design Services, S278 Team) – grahamhemmings@warwickshire.gov.uk

 

Published: 2nd May 2023